SHI Jin, ZHANG Yu-xiao, CHEN Yun-feng, WANG Xiao-kai, WANG Ying-jie. Track alignment irregularity control method for tamping operation of ballasted high-speed railway[J]. Journal of Traffic and Transportation Engineering, 2022, 22(2): 76-86. doi: 10.19818/j.cnki.1671-1637.2022.02.005
Citation: SHI Jin, ZHANG Yu-xiao, CHEN Yun-feng, WANG Xiao-kai, WANG Ying-jie. Track alignment irregularity control method for tamping operation of ballasted high-speed railway[J]. Journal of Traffic and Transportation Engineering, 2022, 22(2): 76-86. doi: 10.19818/j.cnki.1671-1637.2022.02.005

Track alignment irregularity control method for tamping operation of ballasted high-speed railway

doi: 10.19818/j.cnki.1671-1637.2022.02.005
Funds:

National Natural Science Foundation of China 52078035

Science and Technology Research and Development Project of China National Railway Group Co., Ltd. N2020G011

Project of Science and Technology of China Academy of Railway Sciences Co., Ltd. 2020YJ110

More Information
  • Author Bio:

    SHI Jin(1980-), male, professor, PhD, jshi@bjtu.edu.cn

  • Received Date: 2021-09-28
  • Publish Date: 2022-04-25
  • In order to improve the quality of tamping operation of ballasted high-speed railway to meet the requirement of track alignment irregularity control, the influencing factors of lining effect were analyzed according to the operation characteristics of large machine, and the relationships between lining value range, lining strategy, lining value slope rate, equipment accuracy and operation effect were studied. Combined with the analysis result, based on the medium-long wavelength irregularity control theory, the optimization model of lining plan was established, and the method for evaluating the lining effect based on the lining correlation was proposed to realize the effective combination of the factors affecting the lining effect and the formulation process of lining plan. The effectiveness of track alignment irregularity control method was verified in the tamping operation of a ballasted high-speed railway. Research results show that too large or too small lining value, excessive lining value slope rate, unfavorable lining strategy and poor equipment accuracy are easy to lead to poor operation effect of large machine, so it is necessary to strengthen the control and management of the above factors in the formulating process of lining plan. By introducing the lining coefficient into the track alignment irregularity control and effectively controlling to the parameters such as the medium-long wavelength irregularity and the lining limit, the adaptability of the method to the inherent characteristics of tamping machine improves. The method is applied to formulate a lining plan for a certain operation section, and the lining effect meets the requirement of track alignment irregularity management and the characteristics of tamping machine. After the implementation of the plan, the 30 and 300 m vector distance differences reduce to 2 and 7 mm, with a decrease of 50% and 48%, respectively. The static track quality index reduces from 0.89 to 0.64, with a decrease of 28%. The practice proves that the track alignment irregularity control method can effectively improve the regularity of ballasted high-speed railway. 3 tabs, 15 figs, 26 refs.

     

  • loading
  • [1]
    XU Wei-chang. Study on track quality evaluation index for tamping operation of large-type maintenance machine[J]. Railway Engineering, 2014, 54(7): 139-142. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDJZ201407041.htm
    [2]
    YANG Fei, ZHONG Jin-jun, YOU Ming-xi, et al. Research on the effect evaluation index and method for large maintenance machine operation[J]. Railway Standard Design, 2018, 62(12): 28-34. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDBS201812007.htm
    [3]
    ILINYKH A, MANAKOV A, ABRAMOV A, et al. Quality assurance and control system for railway track tamping[J]. MATEC Web of Conferences, 2018, 216: 03004. doi: 10.1051/matecconf/201821603004
    [4]
    RHAYMA N, BRESSOLETTE P, BREUL P, et al. Reliability analysis of maintenance operations for railway tracks[J]. Reliability Engineering and System Safety, 2013, 114: 12-25. doi: 10.1016/j.ress.2012.12.007
    [5]
    WANG Sheng, PAN Ya-jia, DING Kun, et al. Analysis of correction value of horizontal adjustment in continuous operation mode of DCL2-32 continuous tamping machine[J]. Railway Engineering, 2011, 51(7): 138-139. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDJZ201107047.htm
    [6]
    MU Dong-sheng, ZHOU Yu, HAN Yan-bin, et al. Effect of track comprehensive maintenance on geometry irregularity improvement of ballast track in high-speed railway[J]. Journal of Traffic and Transportation Engineering, 2018, 18(5): 90-99. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-JYGC201805011.htm
    [7]
    AUDLEY M, ANDREWS J D. The effects of tamping on railway track geometry degradation[J]. Proceedings of the Institution of Mechanical Engineers, Part F: Journal of Rail and Rapid Transit, 2013, 227(4): 376-391. doi: 10.1177/0954409713480439
    [8]
    SOLEIMANMEIGOUNI I, AHMADI A, ARASTEH KHOUY I, et al. Evaluation of the effect of tamping on the track geometry condition: a case study[J]. Proceedings of the Institution of Mechanical Engineers, Part F: Journal of Rail and Rapid Transit, 2018, 232(2): 408-420. doi: 10.1177/0954409716671548
    [9]
    ZHENG Yao, DONG Wei-min, ZHOU Tao-yong, et al. Influence of ballast grading on tamping effect and parameter optimization[J]. Journal of Wuhan University of Technology (Transportation Science and Engineering), 2019, 43(5): 937-941. (in Chinese) doi: 10.3963/j.issn.2095-3844.2019.05.027
    [10]
    WANG Wei-dong, SONG Shan-yi, YAN Hai-jian, et al. Experimental study on resistance characteristics of ballast bed in different stamping stages[J]. Journal of Central South University (Science and Technology), 2018, 49(8): 2003-2008. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-ZNGD201808021.htm
    [11]
    ZHANG Ya-qing, XU Ping, ZHOU Tao-yong, et al. Study on the effect of tamping parameters on compactness of the ballast bed for the high-speed railway[J]. Journal of Transport Science and Engineering, 2019, 35(2): 11-15. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-CSJX201902003.htm
    [12]
    LIU Jian-xing, WANG Ping, LIU Gan-zhong, et al. Influence of a tamping operation on the vibrational characteristics and resistance-evolution law of a ballast bed[J]. Construction and Building Materials, 2020, 239: 117879.
    [13]
    HE Guo-hua, NIU Huai-jun, GAO Chun-lei, et al. Development of laser collimation system for curve of tamping machine[J]. Railway Engineering, 2014, 54(1): 103-105. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDJZ201401030.htm
    [14]
    SHEN Yan-jun, CEN Min-yi, JIANG Lai-wei, et al. Discussion on evaluation method of fine-tuning scheme for ballasted track of high-speed railway[J]. Geomatics and Spatial Information Technology, 2020, 43(5): 131-135, 139. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-DBCH202005037.htm
    [15]
    WEN Min, LI Rui, BANG SALLING K. Optimization of preventive condition-based tamping for railway tracks[J]. European Journal of Operational Research, 2016, 252(2): 455-465.
    [16]
    SHI Jin, ZHANG Yu-xiao, CHEN Yun-feng, et al. Optimization algorithm and application of precise tamping for speed raising railway based on long-wave regularity[J]. Journal of the China Railway Society, 2022, 44(2): 72-80. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDXB202202010.htm
    [17]
    SHI Jin, ZHANG Yu-xiao, LOU Liang-wei, et al. Optimization and effect of accurate tamping operation link for ballasted track in newly-built high-speed railway[J]. China Railway Science, 2021, 42(6): 8-17. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-ZGTK202106002.htm
    [18]
    WANG Ying-jie, CHU Hang, SHI Jin, et al. Research on the machine tamping quality correlation and sensitive wavelengths of high speed railway ballasted track[J]. Journal of Railway Engineering Society, 2021, 38(1): 37-41, 108. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDGC202101007.htm
    [19]
    LI Yang-teng-long, CEN Min-yi. A method of integer programming for track fine adjustment[C]//SPIE. Sixth International Conference on Electronics and Information Engineering. Washington DC: SPIE, 2015: 97940D.
    [20]
    LI Yang-teng-long, CEN Min-yi, MA Guo-zhi. Study on a novel inspection model of middle and long wave irregularities of track in high-speed railways[J]. Journal of the China Railway Society, 2017, 39(2): 112-118. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDXB201702016.htm
    [21]
    LI Yang-teng-long. Study on track precise inspection and adjustment as well as its regularity optimization for high-speed railways[J]. Acta Geodaetica et Cartographica Sinica, 2018, 47(11): 1562. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-CHXB201811019.htm
    [22]
    WEI Hui, ZHU Hong-tao, ZHAO Guo-tang, et al. Iterative algorithm of HSR ballastless track realignment calculation based on MCO model[J]. Journal of Southwest Jiaotong University, 2015, 50(1): 131-136. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-XNJT201501020.htm
    [23]
    WEI Hui, WU Shi-feng, ZHU Hong-tao. Research on ballast trimming technology based on relative measurement method for ballast track of high-speed railway[J]. Railway Standard Design, 2013, 57(8): 11-15. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-TDBS201308002.htm
    [24]
    WEI Hui, WEI Yu, ZHU Hong-tao. A throw algorithm with versine difference closure for track curve realignment[J]. Journal of Railway Science and Engineering, 2019, 16(7): 1637-1644. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-CSTD201907005.htm
    [25]
    CHEN Qi-jin, NIU Xiao-ji, ZUO Li-li, et al. A railway track geometry measuring trolley system based on aided INS[J]. Sensors, 2018, 18(2): 538.
    [26]
    LI Zai-wei, LEI Xiao-yan, GAO Liang. New numerical simulation method of shortwave track irregularity[J]. Journal of Traffic and Transportation Engineering, 2016, 16(1): 37-45. (in Chinese) http://www.cnki.com.cn/Article/CJFDTOTAL-JYGC201601007.htm